Current Status
Banner is Broken and needs to be fixed
How?
- Adopt Banner/Higher Ed best practices and implement Best in Class Banner Processes
- Improved coordination and communication between units
- Continued upgrading skills and training of staff on Best in Class Processes
- Reconfigure system for Best in Class Banner Processes
Page 3
Download HTML
Activity to Date
- Held process overview training during Facility/Staff institute
- Began process training with Banner Module teams
- Reviewing final proposal, scope of work and contract with Ellucian for services to assist with Banner Evolution.
- Process Improvement Assessment
- Consulting work along
- On demand training Library
- Hosting and DR services
- DBA assistance
- New Modules
Page 4
Download HTML
Focus Area for Optimization
โข Student Recruiting
- Enhance current business processes
- Increase tools used to assist the process
- Phased roll-out of tools starting in 3 months
โข Ellucian and KSU team activities
- Process Improvement Assessment to begin 2-3 weeks after contract is signed โ 4 weeks duration
- Consultants working along with KSU staff โ to begin 4-6 weeks after contract is signed (follows PIA) โ 3 months duration
- On demand training Library to begin 1 week after contract is signed
s Area for Optimization
Page 5
Download HTML
Focus Area for Optimization
โข Financial Aid
- Enhance current business processes
- Further educate student on their role, responsibilities and delivery times
โข Ellucian and KSU team activities
- Process Improvement Assessment to begin 2-3 weeks after contract is signed โ 4 weeks duration
- Consultants working along with KSU staff โ to begin 4-6 weeks after contract is signed (follows PIA) โ 3 months duration
- On demand training Library to begin 1 week after contract is signed
Is ฮ area for Optimization
Page 6
Download HTML
Focus Area for Optimization
โข Billing
- Currently too complex, needs to be rebuilt
- Ellucian and KSU team activities
- Process Improvement Assessment to begin 2-3 weeks after contract is signed โ 4 weeks duration
- Consultants working along with KSU staff โ to begin 4-6 weeks after contract is signed (follows PIA) โ 3 months duration
- On demand training Library to begin 1 week after contract is signed
Page 7
Download HTML
Additional Areas
โข HR Process assessment and work along
- Process Improvement Assessment to begin 2-3 weeks after contract sign โ 4 weeks duration
Consulting work along to begin 4-6 weeks after contract sign (follows PIA) โ 3 months duration
โข Finance Process assessment and work along
- Process Improvement Assessment to begin 2-3 weeks after contract sign โ 4 weeks duration
- Consultants working along with KSU staff โ to begin 4-6 weeks after contract sign (follows PIA) โ 3 months duration
Page 8
Download HTML
Additional Areas
- Ellucian job scheduler (UC4) to begin 4 weeks after contract is signed, 2 months to start production longer for full implementation
- Ellucian Recruiter Implementation (New Module) to begin 7 months after contract is signed, 8 months duration to production (from start)
- Ellucian Banner Degree Works Implementation (New Module) to begin 15 months after contract is signed, 11 months duration to production (from start)
Page 9
Download HTML
Additional Areas
- On demand training Library to begin 1 week after contract is signed
- Hosting and DR services to begin 2 weeks after contract is signed, Test up in 45 days, Production 4-6 months, 5 year commitment
DBA assistance to begin 2 weeks after contract is signed, with a 6 month duration