Focus Area for Optimization

• Student Recruiting

  • Enhance current business processes
  • Increase tools used to assist the process
  • Phased roll-out of tools starting in 3 months

• Ellucian and KSU team activities

  • Process Improvement Assessment to begin 2-3 weeks after contract is signed – 4 weeks duration
  • Consultants working along with KSU staff – to begin 4-6 weeks after contract is signed (follows PIA) – 3 months duration
  • On demand training Library to begin 1 week after contract is signed