Download HTML
Alt US 19 (Seminole Boulevard) Repaving from 101st Avenue N. to East Bay Drive 437624-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From north of 101st AvenueNorth to EastBay Drive |
| Project Start | July 2021 |
| Length | 3.6 miles |
| City | LargoSeminole |
| County | Pinellas |
| Road | Alt US 19SeminoleBoulevard |
| Construction Cost | $5.4 million |
| Estimated Completion | Spring 2022 |
| Contractor | PreferredMaterials, Inc. |
About
All work on this project was completed as of April 8, 2022.
This project is repaving Alt. US 19 (Seminole Boulevard), extending the left turn lanes and modifying median openings between 101st Avenue North in Seminole and East Bay Drive in Largo.
Construction is expected to finish in the spring of 2022.