| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From north of 101st AvenueNorth to EastBay Drive |
| Project Start | July 2021 |
| Length | 3.6 miles |
| City | LargoSeminole |
| County | Pinellas |
| Road | Alt US 19SeminoleBoulevard |
| Construction Cost | $5.4 million |
| Estimated Completion | Spring 2022 |
| Contractor | PreferredMaterials, Inc. |
This project is repaving Alt. US 19 (Seminole Boulevard), extending the left turn lanes and modifying median openings between 101st Avenue North in Seminole and East Bay Drive in Largo.
Construction is expected to finish in the spring of 2022.
Contact Information
Project Information
Sarah Gansz 727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us