← 280.pdf_v_d08172022.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON
Page 1
Download HTML
Tampa Bay
Florida Department of Transportation
Alt US 19 (Seminole Boulevard) Repaving from 101st Avenue N. to East Bay Drive
437624-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From north of 101st AvenueNorth to EastBay Drive |
| Project Start | July 2021 |
| Length | 3.6 miles |
| City | LargoSeminole |
| County | Pinellas |
| Road | Alt US 19SeminoleBoulevard |
| Construction Cost | $5.4 million |
| Estimated Completion | Spring 2022 |
| Contractor | PreferredMaterials, Inc. |
About
All work on this project was completed as of April 8, 2022.
This project is repaving Alt. US 19 (Seminole Boulevard), extending the left turn lanes and modifying median openings between 101st Avenue North in Seminole and East Bay Drive in Largo.
Construction is expected to finish in the spring of 2022.
Contact Information
Project Information
Sarah Gansz 727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us