Tampa Bay Florida Department of Transportation
CR 52/Meridian Avenue/21st Street/Suwanee Way/St. Joe Road Intersection Improvements 439832-5-52-01
Project Details
Work TypeIntersectionImprovement
PhaseDesign
LimitsAt the intersection of CR 52/Meridian Avenue/21st Street/Suwanee Way/St. Joe Road
Length0.162 miles
CityDade City
CountyPasco
RoadCR 52Meridian Avenue
Contact Information
Design Manager Charlie Xie, P.E. 813-975-6287 Charlie.Xie@dot.state.fl.us
Media Contact Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
About
This project will replace the existing T-intersection at CR 52/Meridian Avenue/21st Street with a four-legged signalized intersection at CR 52/Meridian Avenue/21st Street/Suwanee Way/St. Joe Road in Pasco County. The project is currently being designed. Construction is anticipated to begin in 2027.