Tampa Bay Florida Department of Transportation
US 41 Widening from SR 44 to Withlacoochee Trail bridge 257165-3-52-01
Project Details
Work TypeWidening
PhaseCompleted
Limitsfrom SR 44 to south of the Withlacoochee State Trail
Project StartOctober 2, 2023
Length1 mile
CityInverness
CountyCitrus
RoadUS 41
Construction Cost$21.6 Million
Estimated CompletionSummer 2025
ContractorWatson Civil Construction, Inc.
About
As of August 13, 2025, all construction activities associated with this project have been completed.
Contact Information
Project Information
John McShaffrey 813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
This project widened US 41 from SR 44 (W Main Street) to south of the bridge over the Withlacoochee State Trail from a two-lane roadway to a four-lane divided road with bike lanes and sidewalks. New traffic signals were installed at a realigned intersection of US 41 / Montgomery Avenue /Zephyr Street and at the US 41 intersection at the Inverness Regional shopping center. Signal upgrades were made at the US 41 / SR 44 intersection.
The improvements on this project included:
Added one lane in each direction.
Added a median separation.
Added street lighting to all signalized intersections.
Provided bicycle lanes adjacent to travel lane in each direction.
Provided sidewalks on both sides.
Pedestrian safety upgrades at intersections.
Added a dedicated left turn lane for the southbound traffic going to Inverness Middle School.
Provided a shared used path to connect sidewalks to the Withlacoochee State Trail (WST) at the north end of the project. The WST was not impacted by this project.