US 41 Widening from SR 44 to Withlacoochee Trail bridge 257165-3-52-01
| Project Details | |
| Work Type | Widening |
|---|---|
| Phase | Completed |
| Limits | from SR 44 to south of the Withlacoochee State Trail |
| Project Start | October 2, 2023 |
| Length | 1 mile |
| City | Inverness |
| County | Citrus |
| Road | US 41 |
| Construction Cost | $21.6 Million |
| Estimated Completion | Summer 2025 |
| Contractor | Watson Civil Construction, Inc. |
About
As of August 13, 2025, all construction activities associated with this project have been completed.
Contact Information
Project Information
John McShaffrey 813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
This project widened US 41 from SR 44 (W Main Street) to south of the bridge over the Withlacoochee State Trail from a two-lane roadway to a four-lane divided road with bike lanes and sidewalks. New traffic signals were installed at a realigned intersection of US 41 / Montgomery Avenue /Zephyr Street and at the US 41 intersection at the Inverness Regional shopping center. Signal upgrades were made at the US 41 / SR 44 intersection.
The improvements on this project included:
- Added one lane in each direction.
- Added a median separation.
- Added street lighting to all signalized intersections.
- Provided bicycle lanes adjacent to travel lane in each direction.
- Provided sidewalks on both sides.
- Pedestrian safety upgrades at intersections.
- Added a dedicated left turn lane for the southbound traffic going to Inverness Middle School.
- Provided a shared used path to connect sidewalks to the Withlacoochee State Trail (WST) at the north end of the project. The WST was not impacted by this project.