Tampa Bay
Florida Department of Transportation
US 19 Drainage Repairs from Anclote River Bridge to Brittany Park Blvd 434807-3-52-01
| Project Details | |
| Work Type | Drainage repair |
|---|---|
| Phase | Completed |
| Limits | from north of the Anclote River bridge to south of Brittany Park Blvd |
| Project Start | August 2021 |
| Length | .2 miles |
| City | Tarpon Springs |
| County | Pinellas |
| Road | US 19 |
| Construction Cost | $1,422,150 |
| Estimated Completion | Early 2022 |
| Contractor | Gosalia Concrete Constructors, Inc |
About
This project was completed on February 21, 2022.
This project is relocating sidewalk along the west side of US 19 between the Anclote River bridge and Brittany Boulevard in Pinellas County.
Other improvements include the regrading of a linear pond to improve the drainage in the area.
Construction is expected to finish in early 2022.
Contact Information
Project Information
David Alonso 727-575-8300
David.Alonso@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us