US 19 Drainage Repairs from Anclote River Bridge to Brittany Park Blvd 434807-3-52-01
| Project Details |
| Work Type | Drainage repair |
|---|
| Phase | Completed |
|---|
| Limits | from north of the Anclote River bridge to south of Brittany Park Blvd |
|---|
| Project Start | August 2021 |
|---|
| Length | .2 miles |
|---|
| City | Tarpon Springs |
|---|
| County | Pinellas |
|---|
| Road | US 19 |
|---|
| Construction Cost | $1,422,150 |
|---|
| Estimated Completion | Early 2022 |
|---|
| Contractor | Gosalia Concrete Constructors, Inc |
|---|
This project is relocating sidewalk along the west side of US 19 between the Anclote River bridge and Brittany Boulevard in Pinellas County.
Other improvements include the regrading of a linear pond to improve the drainage in the area.
Construction is expected to finish in early 2022.