SR 590 Repaving from Leonard Drive to Delaware Street 441656-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | Leonard Dr to Delaware St |
| Project Start | Fall 2023 |
| Length | 1.5 miles |
| City | Safety Harbor |
| County | Pinellas |
| Road | SR 590 |
| Construction Cost | $2.4 million |
| Estimated Completion | Spring 2024 |
| Contractor | Hubbard Construction Company |
About
As of March 14, 2024, all construction activities associated with this project have been completed.
This project consists of repaving SR 590 between Leonard Drive and Delaware Street in Safety Harbor.
In addition, curb ramps and sidewalks will be modified to meet the Americans with Disabilities Act (ADA) standards.
Construction activities are expected in spring 2024.
Contact Information
Project Information
Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us