← 264.pdf_v_d12222020.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON
Page 1
Download HTML
Tampa Bay
Florida Department of Transportation
I-75 Repaving from Manatee County Line to north of CR 672 (Big Bend Road) 437312-1-32-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | From Manatee County Line to north of CR 672 (Big Bend Road) |
| Project Start | January 2020 |
| City | Apollo Beach Ruskin Sun City Center |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $20.1 million |
| Estimated Completion | Early 2021 |
| Contractor | Preferred Materials. Inc. |
About
Completed On: December 16, 2020
This project is repaving approximately 16 miles along I-75 between the Manatee County Line and CR 672 (Big Bend Road) in Hillsborough County.
Construction on the $20 million project is expected to finish in early 2021.
Contact Information
Project Information
Shiva Moonian 813-612-3200
Shiva.Moonian@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us