I-75 Repaving from Manatee County Line to north of CR 672 (Big Bend Road) 437312-1-32-01
| Project Details |
| Work Type | Repaving |
|---|
| Phase | Completed |
|---|
| Limits | From Manatee County Line to north of CR 672 (Big Bend Road) |
|---|
| Project Start | January 2020 |
|---|
| City | Apollo Beach Ruskin Sun City Center |
|---|
| County | Hillsborough |
|---|
| Road | I-75 |
|---|
| Construction Cost | $20.1 million |
|---|
| Estimated Completion | Early 2021 |
|---|
| Contractor | Preferred Materials. Inc. |
|---|
This project is repaving approximately 16 miles along I-75 between the Manatee County Line and CR 672 (Big Bend Road) in Hillsborough County.
Construction on the $20 million project is expected to finish in early 2021.
Contact Information
Project Information
Shiva Moonian 813-612-3200
Shiva.Moonian@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us