← 1016.pdf_v_d09302026.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON
Page 1
Download HTML
Tampa Bay
Florida Department of Transportation
Alt US 19 (Bayshore Boulevard) Safety Enhancements from Wilson Street to south of Curlew Road 451073-1-52-01
| Project Details | |
| Work Type | Safety Enhancements |
|---|---|
| Phase | Completed |
| Limits | Wilson Street to Curlew Road |
| Project Start | March 23, 2026 |
| Length | 1.9 miles |
| City | Dunedin |
| County | Pinellas |
| Road | Alt US 19 SR 595 |
| Construction Cost | $1.3 million |
| Estimated Completion | Fall 2026 |
| Contractor | Burgess Civil, Inc. |
Contact Information
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
About
As of September 2, 2026, all construction activities associated with this project have been completed.
The purpose of this project is to enhance mobility and safety by adding Rectangular Rapid Flashing Beacon (RRFB) mid-block crossings at the following locations:
just south of Spring Street
northside of San Salvador Drive
southside of San Jose Drive
just north of Mira Vista Drive
just north of Duchess Boulevard
The northside of the Palm Boulevard signalized intersection will also be upgraded to include a pedestrian crossing. Median modifications and driveway modifications are also planned along Alt US 19 (Bayshore Boulevard) in Dunedin.
Construction is underway and expected to be complete in fall of 2026.