Alt US 19 (Bayshore Boulevard) Safety Enhancements from Wilson Street to south of Curlew Road 451073-1-52-01
| Project Details |
| Work Type | Safety Enhancements |
|---|
| Phase | Completed |
|---|
| Limits | Wilson Street to Curlew Road |
|---|
| Project Start | March 23, 2026 |
|---|
| Length | 1.9 miles |
|---|
| City | Dunedin |
|---|
| County | Pinellas |
|---|
| Road | Alt US 19 SR 595 |
|---|
| Construction Cost | $1.3 million |
|---|
| Estimated Completion | Fall 2026 |
|---|
| Contractor | Burgess Civil, Inc. |
|---|
Contact Information
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
As of September 2, 2026, all construction activities associated with this project have been completed.
The purpose of this project is to enhance mobility and safety by adding Rectangular Rapid Flashing Beacon (RRFB) mid-block crossings at the following locations:
just south of Spring Street
northside of San Salvador Drive
southside of San Jose Drive
just north of Mira Vista Drive
just north of Duchess Boulevard
The northside of the Palm Boulevard signalized intersection will also be upgraded to include a pedestrian crossing. Median modifications and driveway modifications are also planned along Alt US 19 (Bayshore Boulevard) in Dunedin.