I-75 Southbound Rest Area Parking Lot expansion Hillsborough County 441083-2-52-01
| Project Details | |
| Work Type | Rest Area Upgrades |
|---|---|
| Phase | Completed |
| Limits | I-75 Southbound Rest Area Hillsborough County |
| Project Start | October 2020 |
| City | Ruskin |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $10,034,122 |
| Estimated Completion | Summer 2022 |
| Contractor | PCS Civil, Inc. |
About
All construction activities on this project were completed on Tuesday, May 31, 2022.
This project replaced the southbound I-75 Rest Area's parking lots with concrete pavement and expanded the truck parking area.
Construction was expected to finish during the summer of 2022.