I-75 Southbound Rest Area Parking Lot expansion Hillsborough County 441083-2-52-01

Project Details
Work TypeRest Area Upgrades
PhaseCompleted
LimitsI-75 Southbound Rest Area Hillsborough County
Project StartOctober 2020
CityRuskin
CountyHillsborough
RoadI-75
Construction Cost$10,034,122
Estimated CompletionSummer 2022
ContractorPCS Civil, Inc.

About

All construction activities on this project were completed on Tuesday, May 31, 2022.

This project replaced the southbound I-75 Rest Area's parking lots with concrete pavement and expanded the truck parking area.

Construction was expected to finish during the summer of 2022.