I-4 Eastbound Auxiliary Lane from 15th Street to 26th Street 445057-2-52-01
Project Details
| Project Details | |
| Work Type | Widening |
|---|---|
| Phase | Construction |
| Limits | 15th Street to 26th Street |
| Project Start | October 16, 2026 |
| Length | 0.7 miles |
| City | Tampa |
| County | Hillsborough |
| Road | I-4 |
| Construction Cost | $10.7 million |
| Estimated Completion | Late 2027 |
| Contractor | Webber, LLC |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
- This project is adding one auxiliary lane in the eastbound direction on I-4 from 15th Street to west of 26th Street in Hillsborough County. Other improvements include:
- widening the I-4 eastbound bridge over 21st/22nd Street
- constructing retaining walls
- installing new LED lighting
- adding signing and pavement markings
- and installing Intelligent Transportation Systems (ITS)
- Construction is anticipated to finish late 2027.
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 445057-2-52-01) Last Updated: 10/19/2026