JACKSON TOWNSHIP DEPARTMENT OF COMMUNITY DEVELOPMENT & ENFORCEMENT DIVISION OF CONSTRUCTION INSPECTIONS

LOCATION: 65 DON CONNOR BLVD.

MAILING ADDRESS: 95 WEST VETERANS HWY. JACKSON NEW JERSEY, 08527

TEL. 732-928-1200 EXT. 1205 FAX 732-928-7861 buildingdept@jacksontwpnj.net

SINGLE FAMILY NEW CONSTRUCTION

APPLICATION CHECK LIST

PRIOR APPROVALS

[ ] 01. Fresh Water Wetlands, Builders Responsibility; contact the Department of Environmental Protection.

  • Letter of Determination.
  • Engineer's Certification.
  • [ ] 02. Ocean county Board of Health approval, if applicable.
  • Septic System, D.C.A. Bulletin 96-3 / prior approval for septic.
  • Well.
  • [ ] 03. Jackson Township Municipal Utility Authority approval, if applicable.
  • City Water
  • City Sewer.
  • [ ] 04. State of New Jersey, Pinelands Commission, if applicable.
  • Letter of Determination
  • Engineer's Certification
  • [ ] 05. Township of Jackson, Zoning Officer a. Zoning Permit Approval.
  • [ ] 06. Township of Jackson, Tree Forester a. Tree Removal Permit
  • [ ] 07. Ocean County Soils Conservation, County Erosion Control Specialist approval, if applicable.
  • Soil Erosion Plan for disturbing more than 5,000 square feet of soil.
  • Preliminary
  • Final

[ ] 08. Proof of Ownership

[ ] 09. Approved Engineering Application

  • Application and Payment made to the Township Zoning Office.
  • Review and approval by the Appointed Engineering Firm.
  • Fees:
  • Preliminary Engineering - $125.00
  • Foundation/As-Built - $ 10.00
  • Final Engineering - $150.00

[ ] 10. Development Fee, determined by Zoning Office, if applicable.

  • Development Fee Form or,
  • C.O.H.A. Fee For.

[ ] 11. Two (2) sets of Architecturally Sealed Plans of the Currently Adopted New Jersey, International Residential Code.

  • Requesting a partial release for a footing and foundation permit requires three sets of Architecturally Sealed Plans.
  • Two (2) sets of Board signed & sealed engineering plans (FULL SIZE) along with Fire Bureau approval seal.
  • [ ] 12. Energy Sheet and Calculations, if not included on the architectural plans. a. Two (2) sets shall be Referencing N.J.A.C. 5:23-2.15(f)1.vi, 2.18(b) and 3.18.
  • [ ] 13. Two (2) sets of the Plumbing and Gas Riser Diagrams shall be submitted, if not included on the architectural plans.
  • [ ] 14. Two (2) sets of the Electrical Layout Diagram shall be submitted, if not included on the architectural plans.
  • [ ] 15. Licensed Contractors.
  • Electrical Contractor
  • Fire Contractor [Special Alarms & Sprinklers]
  • Plumbing Contractor

[ ] 16. HVAC Equipment Specifications. Two (2) sets per different device and letter from the builder or architect giving the size of the heating appliance with a diagram of the duct work and flow rate shown.

[ ] 17. Additional Equipment being installed. Two (2) sets of drawings and specifications for each item:

  • Fireplace f. Generators
  • Decks g. Vacuum Systems
  • Wood & Pellet Stoves h. Fire Sprinkler Systems
  • Elevator i. Solar Heating/Electrical Systems

e. Central Station Alarms

[ ] 18. Warranty Affidavit & Copy of Builders License and, the Inside Bottom of the U.C.C. Approved Permit Jacket [F-100-1] signed by the building Contractor. If owner of the property is building his/her own home, the signature would be by the owner on the inside top are of the Jacket.

[ ] 19. Adopted Building Codes. [Refer to State Website for Year Adopted or ask a Building Department Representative]

  • N.J. Edition of the International Building Code. [Commercial Structures]
  • N.J. Edition of the International Residential Code. [Residential Structures]
  • National Electrical Code.
  • National Plumbing Code.
  • International Energy Conservation Code. [Residential Structures] and,
  • ASHRAE 90.1-
  • International Mechanical Code
  • International Fuel Gas Code
  • Rehabilitation Subcode 5:23-6
  • Barrier-Free Subcode 5:23-7

[ ] 20. First Time Proto Applications.

a. One set of structural drawings is required for the Tax Assessor's Office.