[ ] 08. Proof of Ownership
[ ] 09. Approved Engineering Application
- a.Application and Payment made to the Township Zoning Office.
- b.Review and approval by the Appointed Engineering Firm.
- Fees:
- Preliminary Engineering - $125.00
- Foundation/As-Built - $ 10.00
- Final Engineering - $150.00
[ ] 10. Development Fee, determined by Zoning Office, if applicable.
- a.Development Fee Form or,
- b.C.O.H.A. Fee For.
[ ] 11. Two (2) sets of Architecturally Sealed Plans of the Currently Adopted New Jersey, International Residential Code.
- a.Requesting a partial release for a footing and foundation permit requires three sets of Architecturally Sealed Plans.
- b.Two (2) sets of Board signed & sealed engineering plans (FULL SIZE) along with Fire Bureau approval seal.
- [ ] 12. Energy Sheet and Calculations, if not included on the architectural plans.
a. Two (2) sets shall be Referencing N.J.A.C. 5:23-2.15(f)1.vi, 2.18(b) and 3.18.
- [ ] 13. Two (2) sets of the Plumbing and Gas Riser Diagrams shall be submitted, if not included on the architectural plans.
- [ ] 14. Two (2) sets of the Electrical Layout Diagram shall be submitted, if not included on the architectural plans.
- [ ] 15. Licensed Contractors.
- a.Electrical Contractor
- b.Fire Contractor [Special Alarms & Sprinklers]
- c.Plumbing Contractor
[ ] 16. HVAC Equipment Specifications. Two (2) sets per different device and letter from the builder or architect giving the size of the heating appliance with a diagram of the duct work and flow rate shown.
[ ] 17. Additional Equipment being installed. Two (2) sets of drawings and specifications for each item:
- a.Fireplace f. Generators
- b.Decks g. Vacuum Systems
- c.Wood & Pellet Stoves h. Fire Sprinkler Systems
- d.Elevator i. Solar Heating/Electrical Systems