US 92 (Reynolds St.) Downtown Corridor Improvements from Evers St. to Palmer St. 447015-1-52-01
| Project Details | |
| Work Type | Urban Corridor Improvements |
|---|---|
| Phase | Completed |
| Limits | from west of Evers St to Palmer St. |
| Project Start | April 24, 2021 |
| Length | .108 mile |
| City | Plant City |
| County | Hillsborough |
| Road | Reynolds Street US 92 |
| Construction Cost | $86,342.04 |
| Estimated Completion | Summer 2021 |
| Contractor | Concept Construction and Demolition |
About
All work on this project was completed on June 17, 2021.
This project will build curb extensions (bulb-outs) at five locations for future landscaping along US 92 (Reynolds Street) between Evers Street and Palmer Street in Downtown Plant City.
Construction is anticipated to finish summer of 2021.
Contact Information
Project Information
Kouser Manzer 813-612-3200 Kouser.Manzer@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us