← 1074.pdf_v_d03242026.pdf

Rebuilt HTML โ€” PaddleOCR-VL (Baidu)

Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON

Tampa Bay Florida Department of Transportation
I-4 Florida Regional Advanced Mobility Elements (FRAME) from Hillsborough to Orange counties 445362-3-52-01
Project Details
Work TypeITS
PhaseCompleted
Limitsfrom Hillsborough to Orange
Project StartMarch 15, 2023
CountyHillsborough Polk
RoadI-4
Construction Cost$10.3 million
Estimated CompletionEarly 2026
ContractorTraffic Management Solutions, Inc
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Wednesday, February 4, 2026.
This project installed Intelligent Transportation System (ITS) components to support future connected vehicle infrastructure by installing roadside units along I-4 along Hillsborough, Polk, Osceola, and Orange counties in Florida.
This project was constructed in conjunction with the recently completed Project Number 445362-2-52-01. For more information on that project, please click here.
*Construction cost included original construction contract amount plus approved contract changes. It did not include inspection oversite.