Tampa Bay
Florida Department of Transportation
I-4 Florida Regional Advanced Mobility Elements (FRAME) from Hillsborough to Orange counties 445362-3-52-01
| Project Details | |
| Work Type | ITS |
|---|---|
| Phase | Completed |
| Limits | from Hillsborough to Orange |
| Project Start | March 15, 2023 |
| County | Hillsborough Polk |
| Road | I-4 |
| Construction Cost | $10.3 million |
| Estimated Completion | Early 2026 |
| Contractor | Traffic Management Solutions, Inc |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Wednesday, February 4, 2026.
This project installed Intelligent Transportation System (ITS) components to support future connected vehicle infrastructure by installing roadside units along I-4 along Hillsborough, Polk, Osceola, and Orange counties in Florida.
This project was constructed in conjunction with the recently completed Project Number 445362-2-52-01. For more information on that project, please click here.
*Construction cost included original construction contract amount plus approved contract changes. It did not include inspection oversite.