← 795.pdf_v_d06032022.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Semantic HTML reconstructed from the OCR item tree (headings, text, lists, tables, form fields). overlay ยท view JSON
Page 1
Download HTML
US 92 (Hillsborough Ave) Highway Lighting Improvements from 56th Street to I-4 445554-1-52-01
| Project Details | |
| Work Type | Highway Lighting |
|---|---|
| Phase | Completed |
| Limits | from 56th St. to I-4 |
| Project Start | November 15, 2021 |
| Length | 1.5 miles |
| City | Tampa |
| County | Hillsborough |
| Road | Hillsborough Avenue US 92 |
| Construction Cost | $755,204.35 |
| Estimated Completion | Summer 2022 |
| Contractor | Highway Safety Devices, Inc. |
About
All construction activities associated with this project were completed on Friday, May 6, 2022.
This project replaced and installed new highway lighting along the US 92 (Hillsborough Avenue) corridor from 56th Street to I-4 in Hillsborough County.
Construction is expected to finish summer of 2022.
Contact Information
Project Information
Anna Geismar 813-975-3553
Anna.Geismar@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us