Tampa Bay
Florida Department of Transportation
Bridge Maintenance Hillsborough County Multiple Locations 443832-1-52-01
| Project Details | |
| Work Type | Bridge Maintenance |
|---|---|
| Phase | Completed |
| Limits | I-275, SR 60, I-75, SR 574 |
| Project Start | August 2020 |
| City | Brandon Tampa |
| County | Hillsborough |
| Road | I-275I-75SR 574SR 60 |
| Construction Cost | $1,260,367.40 |
| Estimated Completion | Summer 2022 |
| Contractor | Seacoast, Inc. |
About
As of January 11, 2022, all construction activities associated with this project are now complete.
Contact Information
This project will replace or repair the bearing pads and plates on bridges in Hillsborough County at the following locations;
I-75 at Causeway Boulevard
I -275 over Yukon Street
SR 574 (MLK Blvd) over the Hillsborough River
SR 60 over the Tampa Bypass Canal
SR 60 at the entrance to Tampa International Airport
Construction is expected to finish summer of 2022.
Project Information
Andrew Williams 813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060