Tampa Bay Florida Department of Transportation
SR 60 (Brandon Boulevard) Intersection Upgrades from Brandon Town Center Drive to Gornto Lake Road 436041-1-52-01
Project Details
Work TypeIntersection upgrades
PhaseCompleted
LimitsFrom Brandon Town Center Drive to Gornto Lake Road
Project StartJanuary 3, 2022
CityBrandon
CountyHillsborough
RoadBrandon Boulevard SR 60
Construction Cost$3.7 million
Estimated CompletionFall 2023
ContractorPCS Civil, Inc.
About
All construction activities associated with this project were completed on Friday, November 17, 2023.
Contact Information
Project Information
Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us
This project added turn lanes to SR 60 (Brandon Boulevard) between Brandon Town Center Drive and Gornto Lake Road in Hillsborough County.
Other improvements included:
modifying the existing directional opening by eliminating the eastbound SR 60 (Brandon Boulevard) left turn onto Lake Kathy Drive (motorist to continue eastbound and make a U-turn at the signalized Gornto Lake Road intersection).
replacing the traffic signals at Brandon Town Center Drive.
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us