SUMMARY STATEMENT OF OPERATIONS
For
1980 Swarthmore LLC
Proposed Building
30 South Hope Chapel Road
Block 20901, Lot 15
Township of Jackson
Ocean County, NJ
Prepared by:
D DYNAMIC ENGINEERING
5 Greentree Centre, Suite 406
Marlton, NJ 08053
(856) 334-2000
July 2025
Last Revised February 2026
DEC # 3342-99-007
Page 2
Download HTML
The information provided within this Summary Statement of Operations serves as a general guideline only and is not intended to limit the flexibility of the proposed use or business.
A. PROJECT DESCRIPTION
The subject site is specifically identified as Lot 15 in Block 20901, as shown on the official Tax Maps of the Township of Jackson, Ocean County, New Jersey and consists of approximately 1.13 acres (49,270 SF). Under existing conditions, the property is developed as a single-family home and adjacent former contractor's yard. According to the Official Zoning Map for the Township of Jackson, the property is located within the RGC-2 (Regional Growth Commercial) Zone. The proposed project consists of constructing a 3-story business office, consisting of 14,979 SF. The proposed development also includes accompanying site improvements including parking areas, driveways, landscaping, lighting and stormwater management facilities.
The subject parcel is located in the northwest quadrant of the intersection of South Hope Chapel Road (Ocean County Route 639) and Garden Street. The site is bordered to the north by commercial development, to the east by South Hope Chapel Road (C.R. 547), with residential development beyond to the west.
B. PROPOSED BUSINESS
1. Hours of Operation
The hours of operation for the proposed office building are Monday through Saturday, 8 AM to 5 PM.
2. Number of Employees
a. Office Building โ Per multiple sources the current standard ratio employee to square footage of office space is 1 employee per 200 SF of office space. Therefore, the estimated number of employees is approximately +/- 75 employees.
3. Estimated Number of Truck Traffic
It is anticipated that box trucks (SU-30) will make deliveries as needed to the proposed facility. Deliveries via tractor trailers are not expected. Deliveries will occur between 8:00 AM and 4:30 PM.
4. Trash Removal
Bulk trash is expected to be stored in the exterior proposed trash enclosure and removed by a private waste hauler on an as needed basis โ typically 1-2 times/week. Recycling consisting of glasses, plastic, boxes, cardboard and paper packages, are stored in a container in the exterior trash enclosure and removed by the recycling hauler on an as needed basis โ typically 1 time/week.