SR 39 (James L. Redman Parkway) Repaving from Charlie Griffin Road to Alexander Street 440733-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | from Charlie Griffin Road to Alexander Street |
| Project Start | May 30, 2023 |
| Length | .6 miles |
| City | Plant City |
| County | Hillsborough |
| Road | James L Redman Parkway SR 39 |
| Construction Cost | $3.3 million |
| Estimated Completion | Early 2024 |
| Contractor | CW Roberts Contracting, Inc. |
About
All construction activities associated with this project were completed on Thursday, March 14, 2024.
This project repaved SR 39 (James L. Redman Parkway) between Charlie Griffin Road and Alexander Street in Plant City.
Additional improvements:
Contact Information
Project Information
Maricelle Venegas 813-975-6204
RoadWork@dot.state.fl.us
- added a right turn lane from southbound James L. Redman Parkway onto westbound Alexander Street
- widened the existing right turn lane from Alexander Street onto southbound James L. Redman Parkway
The $3.3 million project began May 30, 2023, and finished March 14, 2024.