Southwest Florida Florida Department of Transportation
I-75 at SR 951 425843-2
| Project Details | |
| Work Type | Interchange Construction |
|---|---|
| Phase | Construction |
| Limits | I-75 at SR 951 (Collier Boulevard) Interchange and Collier Boulevard from Business Circle South to City Gate Drive. |
| Project Start | Early 2023 |
| Length | 1.3 miles |
| City | Naples |
| County | Collier |
| Road | I-75 SR 951 |
| Construction Cost | $97 million |
| Estimated Completion | Early 2027 |
Contact Information
Communications Team Jennifer Dorning 239-338-7723 Jennifer.Dorning@dot.state.fl.us
Construction Project Manager Alex Ruiz (941) 708-4419 Alex.Ruiz@dot.state.fl.us
About
The Florida Department of Transportation (FDOT) District One is preparing design plans to reconstruct the I-75 interchange with SR 951 (Collier Boulevard) in Collier County. The new interchange will include two new ramps over SR 84 (Davis Boulevard) to provide direct interstate access. The existing I-75 bridges over SR 951 will remain. New bridges to accommodate ramp traffic will be constructed adjacent to the existing I-75 bridges over SR 951.