← 1043.pdf_v_d05282024.pdf

Rebuilt HTML โ€” PaddleOCR-VL (Baidu)

Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON

Tampa Bay Florida Department of Transportation
I-75 over the Withlacoochee River - Deck Preservation 445831-1-52-01
Project Details
PhaseCompleted
Project StartMarch 2024
CityBrooksville Ridge Manor
CountyHernando
RoadI-75
Construction Cost$269,000
Estimated CompletionSummer 2024
ContractorBridge Masters Construction, LLC
About
As of May 17, 2024, all work was completed and the project was final accepted from the contractor.
Work on this project included minor concrete repairs, bridge cleaning, and deck sealing with methacrylate to preserve the bridge decks on both northbound and southbound I-75 over the Withlacoochee River at the Hernando County / Sumter County line. This location is approximately 4.5 miles north of US 98/SR 50 (Exit 301) and just under 2 miles south of Sumter CR 673 (Exit 309).
Nighttime lane closures were used, as needed.
Contact Information
Project Information
John McShaffrey 813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us