SR 78 from west of Santa Barbara Boulevard to east of Del Prado Boulevard 450723-1
| Project Details | |
| Work Type | Construction Work |
|---|---|
| Phase | Construction |
| Limits | west of Santa Barbara Boulevard to east of Del Prado Boulevard |
| Project Start | Late 2026 |
| Length | 2.489 miles |
| City | Cape Coral |
| County | Lee |
| Road | SR 78 |
| Construction Cost | $6.89 million |
| Estimated Completion | Late 2027 |