Tampa Bay
Florida Department of Transportation
SR 60 Repaving from Turkey Creek Road to SR 39 446051-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | from west of Turkey Creek Rd to west of SR 39 |
| Project Start | July 27, 2023 |
| Length | 3 miles |
| City | Plant City |
| County | Hillsborough |
| Road | SR 60 |
| Construction Cost | $5.5 million |
| Estimated Completion | Early 2024 |
| Contractor | CW Roberts Contracting, Inc |
About
All construction activities associated with this project were completed on Monday, March 4, 2024.
The FDOT project repaved SR 60 from west of Turkey Creek Road to west of SR 39 in Hillsborough County.