CR 54 Repaving from west of Flint Drive to US 301 447950-1-52-01
| Project Details | |
| Work Type | Resurfacing |
|---|---|
| Phase | Completed |
| Limits | west of Flint Drive to US 301 (Gall Blvd.) |
| Project Start | January 5, 2026 |
| Length | 1.3 miles |
| City | Zephyrhills |
| County | Pasco |
| Road | 5th Avenue CR 54 Pure Water Way |
| Construction Cost | $2.3 million |
| Estimated Completion | Summer 2026 |
| Contractor | Preferred Materials, Inc. |
About
As of July 7, 2026, all construction activities associated with this project have been completed.
The purpose of the project was to preserve and extend the life of the existing CR 54 (Pure Water Way / 5th Avenue) pavement, provide safety modifications, improve ADA deficiencies, improve side slopes and shoulder treatments, upgrade or replace nonstandard guardrail and end treatments, repair existing sidewalks, and replace/refresh signs and pavement markings.
Contact Information