← 1077.pdf_v_d07082026.pdf

Rebuilt HTML โ€” PaddleOCR-VL (Baidu)

Semantic HTML reconstructed from the OCR item tree (headings, text, lists, tables, form fields). overlay ยท view JSON

CR 54 Repaving from west of Flint Drive to US 301 447950-1-52-01

Project Details
Work TypeResurfacing
PhaseCompleted
Limitswest of Flint Drive to US 301 (Gall Blvd.)
Project StartJanuary 5, 2026
Length1.3 miles
CityZephyrhills
CountyPasco
Road5th Avenue CR 54 Pure Water Way
Construction Cost$2.3 million
Estimated CompletionSummer 2026
ContractorPreferred Materials, Inc.

About

As of July 7, 2026, all construction activities associated with this project have been completed.

The purpose of the project was to preserve and extend the life of the existing CR 54 (Pure Water Way / 5th Avenue) pavement, provide safety modifications, improve ADA deficiencies, improve side slopes and shoulder treatments, upgrade or replace nonstandard guardrail and end treatments, repair existing sidewalks, and replace/refresh signs and pavement markings.

Contact Information

Project Information

John McShaffrey (813) 975-6930 john.mcshaffrey@dot.state.fl.us

Media Contact

Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us