SR 583 (56th St) Corridor Lighting Upgrades from Hillsborough Ave to Puritan Rd 254677-5-06
| Project Details | |
| Work Type | Safety Improvements |
|---|---|
| Phase | Completed |
| Limits | from Hillsborough Ave to Puritan Rd |
| Project Start | September 15, 2021 |
| City | Tampa |
| County | Hillsborough |
| Road | 56th Street SR 583 |
| Construction Cost | $191,693.33 |
| Estimated Completion | Early 2022 |
| Contractor | Cone & Graham, Inc. |
About
As of November 5, 2021, all construction activities associated with this project are now complete.
This design-build project is making improvements to the roadway lighting along 56th Street (SR 583) from Hillsborough Avenue to Puritan Road in Hillsborough County.
Improvements include retrofitting existing roadway lighting fixtures with LED luminaries and hardware as necessary to light the roadway to current standards.
Status: Construction is anticipated to finish in early 2022