I-175 Concrete Pavement Repairs from 16th Street S to 4th Street S 445864-1-52-01
| Project Details | |
| Work Type | Concrete Pavement Rehabilitation |
|---|---|
| Phase | Completed |
| Limits | from 16th Street S to 4th Street S |
| Project Start | February 27, 2025 |
| Length | 1 mile |
| City | St. Petersburg |
| County | Pinellas |
| Road | I-175 |
| Construction Cost | $5.8 million |
| Estimated Completion | Early 2026 |
| Contractor | Watson Civil Construction, Inc. |
About
As of March 30, 2026, all construction activities associated with this project have been completed.
This project involves repairing or replacing concrete slabs on I-175 from 16th Street South to 4th Street South in Pinellas County.
The project will also repair a box culvert which runs along this I-175 corridor.
Construction activities are expected to finish during early 2026.