← 366.pdf_v_d08262024.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Semantic HTML reconstructed from the OCR item tree (headings, text, lists, tables, form fields). overlay ยท view JSON
Page 1
Download HTML
Traffic Management System - City of Tampa Arterials 424213-3-52-01
| Project Details | |
| Work Type | Arterial Traffic Management System |
|---|---|
| Phase | Completed |
| Limits | City of Tampa |
| Project Start | October 2020 |
| City | Tampa |
| County | Hillsborough |
| Construction Cost | $38.4 million |
| Estimated Completion | Summer 2024 |
| Contractor | Traffic Control Devices, Inc. |
About
All construction activities associated with this project were completed on Friday, August 16, 2024.
This design-build project upgraded 402 traffic signals and installing 98 miles of new fiber conduit and other communication components to enhance the connectivity throughout the City of Tampa.
This contract combined work from projects 424213-3,424213-4 and 424213-6 into a single construction contract.
Contact Information
Project Information
Maricelle Venegas 813-975-6204
RoadWork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us