I-75 Pavement Rehabilitation from Broadway Avenue to SR 582 (Fowler Avenue)
443630-2-52-01
| Project Details | |
| Work Type | Rigid Pavement Rehabilitation |
|---|---|
| Phase | Construction |
| Limits | from BroadwayAvenue to S. of SR 582 (Fowler Avenue) |
| Project Start | December 9, 2024 |
| Length | 6.037 Miles |
| City | Brandon |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $125.6 million (combined FPN: 445317-1 and 445317-2) |
| Estimated Completion | 2028 |
| Contractor | Webber, LLC |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
This project includes rigid pavement rehabilitation for concrete pavement slabs of the existing roadway, shoulders and select I-75 ramps from Broadway Avenue to Fowler Avenue in Hillsborough County.
Lighting, signage, and pavement marking safety enhancements will also be included in this project.
Work requiring lane and ramp closures will occur at night between 10 p.m. and 5:30 a.m.
Motorists are reminded to use caution when traveling through the work zone and remain alert for construction workers.
Construction activities are estimated to finish during 2028.
This project is being constructed in conjunction with the widening of I-75 from the Tampa Bypass Canal to Fowler Avenue (FPNs: 445317-1-52-01 and 445317-2-52-01).
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 443630-2-52-01)
Last Updated: 11/18/2025