Tampa Bay Florida Department of Transportation
US 41 New Traffic Signal at Universal Drive in Hillsborough County 254677-5-30
Project Details
Work TypeNew Traffic Signal
PhaseCompleted
Project StartJanuary 19, 2023
CitySun City Center
CountyHillsborough
RoadUS 41
Construction Cost$800,000
Estimated CompletionEarly 2024
ContractorCone & Graham, Inc.
Contact Information
Project Information
Maddie Pfingsten
727-575-8334
roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia @dot.state.fl.us
About
As of January 30, 2024, all construction activities associated with this project have been completed.
This construction project is addressing safety improvements with the construction of a new traffic signal at S US Highway 41 at Universal Drive in Hillsborough County.
Elements of work shall include, but are not limited to, installation of the signal mentioned above, roadway resurfacing, sidewalk construction, and pedestrian features as necessary to accommodate pedestrian traffic with minimum impact to the current vehicular traffic patterns. Additional improvements include widening the curve south of Universal Drive to allow southbound right turns.