US 92 (4th Street N.) Median Modifications from 30th Ave N. to 94th Ave N. 439401-1-52-01

Project Details
Work TypeMedian Modifications
PhaseCompleted
Limitsfrom 30th Ave N. to 94th Ave N.
Project StartApril 24, 2023
Length4 miles
CitySt. Petersburg
CountyPinellas
Road4th Street US 92
Construction Cost$7.1 million
Estimated CompletionSummer 2024
ContractorPreferred Materials

Contact Information

Project Information

Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us

Media Contact

Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us

About

As of July 25, 2024, all construction activities associated with this project have been completed.

This project includes extending left turn lane storage at nine signalized intersections and 15 left turn lanes at existing median openings along the corridor.

Some existing median openings will be modified, lengthening the left turn lane storage, and others will be closed. Additionally, nine mid-block pedestrian crossings will be built. The median closures and turn lane extensions will improve safety and traffic flow. The new crosswalks with pedestrian signals will allow pedestrians to cross US 92 (4th St. N) at designated locations more safely. U-turn locations are available throughout the corridor to access businesses.

Construction is underway and anticipated to be complete in summer 2024.