← 1122.pdf_v_d08112026.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Content placed at each item's bbox to mirror the original PDF layout (font sizes are estimated). overlay ยท view JSON
Page 1
Download HTML
Tampa Bay
Florida Department of Transportation
SR 687 (4th Street N) Repaving from 106th Avenue N to 119th Avenue N 456060-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | SR 687 (4th Street N) from 106th Avenue N to 119th Avenue N |
| Project Start | February 24, 2026 |
| Length | 1 mile |
| City | St. Petersburg |
| County | Pinellas |
| Road | 4th Street SR 687 |
| Construction Cost | $1.4 million |
| Estimated Completion | Summer 2026 |
| Contractor | Preferred Materials, Inc. |
About
As of July 28, 2026, all construction activities associated with this project have been completed.
The purpose of this project is to preserve and extend the life of the existing pavement through resurfacing along this section of SR 687 (4th Street N) in Pinellas County
Construction is underway and expected to be complete in the summer of 2026.
Contact Information
Project Information
Maddie Griffin 727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us