Tampa Bay
Florida Department of Transportation
SR 685 (Tampa St and Florida Ave) Railroad Crossing Replacements at Polk Street
437823-1-52-01
| Project Details | |
| Work Type | Railroad Crossing replacements |
|---|---|
| Phase | Completed |
| Limits | Tampa St and Florida Ave at Polk Street |
| Project Start | November 6, 2023 |
| City | Tampa |
| County | Hillsborough |
| Road | Florida Avenue (Hillsborough) Tampa Street |
| Construction Cost | $341,000.00 |
| Estimated Completion | Early 2024 |
| Contractor | Burgess Civil, LLC |
All construction activities associated with this project were completed on Friday, February 16, 2024.
This project is rebuilding the CSX railroad tracks along Polk Street at Tampa Street and Florida Avenue in downtown Tampa.
These intersections will be completely closed while the railroad crossings are replaced.
Traffic will be detoured around each work zone.
About
Construction activities are anticipated to begin November 2023 and finish during early 2024.
Contact Information
Project Information
Maricelle Venegas 813-975-6060
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us