US 92 (Gandy Boulevard) Ramp Intersection Improvement at 94th Avenue 446973-1-52-01

Project Details
Work TypeOperational Improvement
PhaseCompleted
LimitsEastbound off ramp at 94th Avenue N and the Frontage Road at 94th Avenue N.
Project StartMay 4, 2024
CitySt. Petersburg
CountyPinellas
RoadGandy Boulevard US 92
Construction Cost$2.1 million
Estimated CompletionSpring 2025
ContractorPreferred Materials Inc.

About

As of March 14, 2025, all construction activities associated with this project have been completed.

This project will make operational improvements to the Gandy Boulevard off ramp and the frontage road at 94th Avenue N. Right and left turns lanes will be added to the frontage road in this area.

Construction is underway and expected to be complete in spring 2025.