← 555.pdf_v_d05252023.pdf
Rebuilt HTML โ PaddleOCR-VL (Baidu)
Semantic HTML reconstructed from the OCR item tree (headings, text, lists, tables, form fields). overlay ยท view JSON
Page 1
Download HTML
I-4 Westbound Weigh Station New Access Lane 443320-1-52-01
| Project Details | |
| Work Type | New Access Lane |
|---|---|
| Phase | Completed |
| Limits | between the I-4 westbound weigh station and Mango Road |
| Project Start | January 17, 2023 |
| Length | .341 miles |
| City | Dover |
| County | Hillsborough |
| Road | I-4 |
| Construction Cost | $1.4 million |
| Estimated Completion | Summer 2023 |
| Contractor | C.W. Roberts Contracting, Inc. |
About
This project lengthened the acceleration merge lane from the I-4 westbound weigh station near Mango Road in Hillsborough County.
Construction activities were completed on Monday, May 22, 2023.
Contact Information
Project Information
Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us