Tampa Bay Florida Department of Transportation
SR 693 (Pasadena Ave) Repaving from Matthews Rd/Shore Dr. to Central Ave. 440254-2-52-01
Project Details
Work TypeRepaving and Business Access Transit (BAT) lane
PhaseCompleted
Limitsfrom north of Matthews Rd/Shore Dr. to south of Central Ave.
Project StartFall 2021
CitySouth Pasadena St. Petersburg
CountyPinellas
RoadPasadena Avenue SR 693
Construction Cost$1.6 million
Estimated CompletionSpring 2022
ContractorPreferred Materials, Inc.
About
All construction activities associated with this project were completed on May 15, 2022.
This project will repave Pasadena Ave. and add a Business Access Transit (BAT) lane for bus rapid transit.
Construction activities are anticipated to begin in the fall of 2021 and be complete in the Spring of 2022.
Contact Information
Project Information
Matt Kappler 727-575-8300
matthew.kappler@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us