Tampa Bay Florida Department of Transportation
I-75 at SR 52 Interchange Improvements 454668-1-52-01
Project Details
Work TypeInterchange Improvement
PhaseCompleted
LimitsI-75 and SR 52 interchange area
Project StartApril 26, 2026
CitySan Antonio
CountyPasco
RoadI-75 SR 52
Construction Cost$2.1 million
Estimated CompletionOctober 17, 2026
ContractorC.W. Roberts Contracting, Incorporated
About
As of October 17, 2026, all construction activities associated with this project have been completed.
Interchange improvements that were constructed with this project included the following:
Re-striped the existing pavement to provide a 2-lane northbound I-75 exit ramp to SR 52.
Provided a 2-lane ramp from westbound SR 52 to the southbound I-75 entrance ramp.
Provided dual left turn lanes from eastbound SR 52 to the entrance ramp onto northbound I-75.
Provided two receiving lanes on the northbound I-75 entrance ramp.
Reconfigured the existing lanes on westbound SR 52 from Pasco Road to I-75 accordingly.
Contact Information
Project Information John McShaffrey 813-975-6930 john.mcshaffrey@dot.state.fl.us