Florida Department of Transportation
I-75 Concrete Bridge Deck Repairs over the Alafia River Bridge and Other Locations
445828-1-52-01, 445833-1-52-01
| Project Details | |
| Work Type | Concrete Bridge Rehabilitation |
|---|---|
| Phase | Completed |
| Limits | Over the Alafia River Bridge and Other Locations |
| Project Start | October 28, 2024 |
| City | Tampa |
| County | Hillsborough |
| Road | I-75 |
| Construction Cost | $1.7 million |
| Estimated Completion | Fall 2025 |
| Contractor | Bridge Masters Construction, LLC |
About
All construction activities associated with this project were completed on Tuesday, August 26, 2025.
This project repaired and replaced the concrete pavement along Interstate 75 roadway over the Alafia River Bridge and other locations (56th Street Bridge over Hillsborough River, Ashley Street entrance ramp over Laurel Street, and northbound I-275 over I-75) throughout Hillsborough County.
Contact Information