Tampa Bay
Florida Department of Transportation
SR 580 (Skinner Boulevard) Improvements from Alt US 19 (Broadway) to Bass Boulevard
447535-1-52-01
| Project Details | |
| Work Type | Road Improvements |
|---|---|
| Phase | Completed |
| Limits | from Alt US 19 (Broadway) to Bass Boulevard |
| Project Start | October 28, 2024 |
| Length | 0.5 Miles |
| City | Dunedin |
| County | Pinellas |
| Road | SR 580 |
| Construction Cost | $9.2 million |
| Estimated Completion | Early 2026 |
| Contractor | De Moya Highway Infrastructure LLC |
About
As of December 4, 2025, all construction activities associated with this project have been completed.
FDOT is committed to enhancing the safety and mobility of our residents and visitors. This improvement project in Dunedin includes:
Contact Information
Lane reduction from four to two lanes between Alt 19/ Broadway and Oak Street
Roundabouts at Douglas Avenue and Highland Avenue
foot-wide concrete sidewalks connecting to the Pinellas Trail
On-street parking, bus bays and bicycle lanes
Adding a permanent pedestrian crossing signal at the Pinellas Trail
New mast arm signal Bass Boulevard/Main Street
Decorative street lighting
Raised median (landscaping opportunity)
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
For additional information on this FDOT/Dunedin partnership, please visit:
https://dunedin-fl.civilspace.io/en/projects/fdot-skinner-boulevard-improvement-project
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
A Public Meeting was held on June 27, 2023, at Dunedin City Hall and virtually. To view the display exhibits and presentation shown at the meeting, please see the links below in the Project Files section.
Construction is expected to be complete in early 2026.