SR 553 (Park Road) Repaving from US 92 (Baker Street) to north of I-4 441664-1-52-01
| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | from US 92 (Baker Street) to north of I-4 |
| Project Start | August 15, 2025 |
| Length | 1.14 Miles |
| City | Plant City |
| County | Hillsborough |
| Road | SR 553 |
| Construction Cost | $4.6 million |
| Estimated Completion | Fall 2026 |
| Contractor | Hubbard Construction Company |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Saturday, October 17, 2026.
This project repaved Park Road (SR 553) from Baker Street to north of I-4 in Plant City.
Additional improvements included the installation of sidewalk, signing, pavement markings, signalization, lighting, and utility adjustments.
The $4.6 million repaving project was expected to finish fall of 2026.