Tampa Bay Florida Department of Transportation
Alt US 19 (Myrtle Avenue) Railroad Crossing Replacement between Hart Street and Maple Street 437553-1-52-01
Project Details
Work TypeRail Road Crossing Replacement
PhaseDesign
LimitsAlt US 19 (Myrtle Avenue) between Hart Street and Maple Street
Length0.03 mile
CityClearwater
CountyPinellas
RoadAlt US 19 Myrtle Avenue
Contact Information
Design Manager
Anh-Thu Nguyen, PE
813-975-6197
Anh-Thu.Nguyen@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
About
This project will replace the existing railroad crossing along this section of Alt US 19 (N Myrtle Avenue). Damaged sidewalks will also be replaced, and detectable warning surfaces will be added on all sidewalks approaching the railroad crossing.
Construction is anticipated to begin in 2027.