Lee County Rest Area Feasibility Study
Financial Project Indentification Number: 452377-1-22-01
LEGEND X = No โ = Yes
ALTERNATIVES EVALUATION MATRIX
ALTERNATIVE #
EVALUATION CRITERIA No Build Alternative # 1 Hybrid Flow Alternative # 2 Normal Flow Alternative # 3 Clockwise Flow
Description Traffic Pattern Counter-Clockwise Counter-Clockwise Counter-Clockwise Clockwise
Truck Parking Options Maintains the existing Facility as-is Provides both "Pull-Thru" and "Back-In" Provides both "Pull-Thru" and "Back-In" Provides both "Pull-Thru" and "Back-In"
Purpose & Need
Improves Safety Condition X โ โ โ
Increases Truck Parking X โ โ โ
Improves Modal Relationships X โ โ โ
# of Parking Spaces
Truck 43 139 121 143
Personal Vehicle 75 51 51 48
Sociocultural Resources
Provides multimodal mobility and accessibility โ โ โ โ
Archeological & Historic Sites X X X X
Utilities
Cost effective utility connections โ โ โ โ
Drainage and Wetlands
Impacted Wetlands (acres) (includes secondary impacts) 0 6.2 6.6 6.4
Potential impacts to existing drainage infrastructure X Minor Minor Minor
Threatened & Endangered Species X X X X
Connection to Daniels Parkway sidewalks X โ โ โ
Connection to existing Daniels Parkway bus stop X โ โ โ
Enhanced Amenities
Expanded Rest Room Facilities X โ โ โ
Right Of Way
Requires Additional Right of Way X X X X
Dog Walk / Park โ โ โ โ
Picnic Shelters โ โ โ โ
Children's Recreational Area X โ โ โ
Walking Trail X โ โ โ
Lake View areas โ โ โ โ
Informational placards โ โ โ โ
Truck Washing / Maintenance Area X โ โ โ
Estimated Costs
Wetland Mitigation $0 $500,000 $500,000 $500,000
Right of Way $0 $0 $0 $0
Design $0 $3,500,000 $3,500,000 $3,500,000
Construction (includes cost of building) $0 $37,000,000 $37,000,000 $37,000,000
Construction Engineering & Inspection $0 $2,960,000 $2,960,000 $2,960,000
Preliminary Estimate of Total Project Costs $0 $43,960,000 $43,960,000 $43,960,000
Preliminary Analysis - Subject to Change