ImageCity of Harrisonburg
TIMMONS GROUPChicago Avenue & Waterman Drive Corridor
YOUR VISION ACHIEVED THROUGH OURS.Preliminary Planning Cost Estimate - March 2025
City of Harrisonburg, Virginia
Chicago Avenue SB (Mt Clinton Pike to Shenandoah Street)
SUMMARY OF BUDGET PHASESC&G + 6' Facility
Preliminary Engineering (PE)$ 202,000.00
Right of Way (RW)$ 558,000.00
Construction (CN)$ 915,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 1,675,000.00
Chicago Avenue SB (Shenandoah Street to Greystone Street) SUMMARY OF BUDGET PHASESC&G + 10' Facility
Preliminary Engineering (PE)$ 222,000.00
Right of Way (RW)$ 1,253,000.00
Construction (CN)$ 1,005,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 2,480,000.00
Chicago Avenue SB (Greystone Street to Rockingham Drive) SUMMARY OF BUDGET PHASES
C&G + 10' Facility
Preliminary Engineering (PE)$ 137,000.00
Right of Way (RW)$ 333,000.00
Construction (CN)$ 618,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 1,088,000.00
Waterman Drive (Chicago Avenue to Quarry Heights Property) SUMMARY OF BUDGET PHASESC&G + 10' Facility
Preliminary Engineering (PE)$ 182,000.00
Right of Way (RW)$ 410,000.00
Construction (CN)$ 825,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 1,417,000.00
W Market Street Crossing (Quarry Heights Property towards Thomas Harrison Middle School)
SUMMARY OF BUDGET PHASESSignalized Crossing + 10' Facility
Preliminary Engineering (PE)$80,000.00
Right of Way (RW)$126,000.00
Construction (CN)$479,000.00
TOTAL RECOMMENDED PROJECT BUDGET$685,000.00
Trail Connection to Friendly City Trail (from W Market Street) SUMMARY OF BUDGET PHASES10' Facility
Preliminary Engineering (PE)$ 168,000.00
Right of Way (RW)$ 210,000.00
Construction (CN)$ 759,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 1,137,000.00